Hormuz Crisis Pushes Thai Giant SCG to Rebuild Its $5.4bn Vietnam Petrochemical Plant Around US Ethane

high active production shutdown
📅
Published OnNovember 16, 2026
🌍
LocationLong Son Island, Vietnam
🏭
SupplierLong Son Petrochemicals (SCG Chemicals)
📦
SectorPetrochemicals
🎯
Impacted ClientVietnamese plastics converters and packaging manufacturers
⚙️
Critical ComponentNaphtha and propane feedstock
💰
Financial Impact$120,000,000

Thai conglomerate Siam Cement Group (SCG) is reshaping the feedstock strategy of its $5.4 billion Long Son Petrochemicals (LSP) complex in southern Vietnam, moving away from Middle Eastern naphtha and propane toward ethane shipped from the United States. The decision is a direct consequence of the disruption of shipping through the Strait of Hormuz, which has starved Asian crackers of Gulf feedstock since the US-Iran war escalated at the end of February 2026. The complex has been idle since mid-May, and its restart is now expected around mid-2027, once the conversion work is completed.

How the Hormuz crisis shut down Vietnam's only cracker

Located on Long Son Island, in an area that now belongs to Ho Chi Minh City after the merger with the former Ba Ria-Vung Tau province, LSP is Vietnam's first fully integrated petrochemical complex. It can produce about 950,000 tons of ethylene and 400,000 tons of propylene a year, which are turned into polyethylene and polypropylene, the plastic resins used in packaging, consumer goods, pipes and automotive parts. Roughly half of the naphtha and propane the plant consumed came from the Middle East, which left it heavily exposed when tanker traffic through the strait collapsed in March.

SCG reacted in two steps. On March 10, 2026, it informed the Stock Exchange of Thailand that its Rayong Olefins plant in Thailand was being temporarily shut down. On April 22, the group announced that LSP would follow, explaining that tensions around Hormuz had disrupted logistics and created severe procurement bottlenecks for naphtha and propane. The company said it had tried to limit the damage by buying feedstock from suppliers located outside the strait, but prices and supply continuity remained unfavorable, so the Vietnamese complex stopped production around mid-May 2026.

SCG presented the halt as a way to reduce operating risks during a prolonged period of uncertainty. It estimated that keeping the idle site in good condition would cost about 250 million baht per month in fixed cash expenses, and it decided to use the downtime for maintenance work and to speed up the ethane project it had already been preparing.

A plant with a turbulent start

The current shutdown is the second long interruption in the short life of the complex. LSP began full commercial operations on September 30, 2024, but halted production only a few weeks later because of weak margins in the regional polyolefins market, which was flooded by new Chinese capacity. It restarted in August 2025 after a pause of roughly ten months, helped by lower crude prices, and had been running for less than nine months when the Gulf crisis forced it offline again. Those repeated stops have weighed on SCG Chemicals, which has reported losses linked to the Vietnamese unit since 2024.

The fix: a long-term bet on US ethane

The answer SCG has chosen is the Long Son Petrochemical Enhancement project, known as LSPE. Under a 15-year agreement signed with Texas-based midstream operator Enterprise Products Partners, the plant will receive about 1 million tonnes of US ethane per year on a free-on-board basis from the US Gulf Coast. To carry it across the Pacific, SCG Chemicals has chartered five very large ethane carriers from Japan's Mitsui O.S.K. Lines, also for 15 years. In Vietnam, the project includes two refrigerated ethane storage tanks with a capacity of 55,000 tonnes each and modifications that will allow the cracker to run on up to 70% ethane, while keeping the ability to process naphtha and propane when market conditions favor them. SCG has put the total investment for the upgrade at around $700 million.

Cost is a central argument. SCG estimates that US ethane is about 40% cheaper than naphtha, a gap that could move Long Son down the regional cost curve and allow it to stay profitable at lower selling prices. Security of supply is now just as important. Once the conversion is finished, the group aims to cut the share of feedstock coming from the Middle East to below 25%, compared with about half before the crisis. The company also says the switch will reduce the plant's greenhouse gas emissions.

Restart timeline slips to mid-2027

The schedule has moved several times. In October 2026, SCG said LSP had moved from a preservation shutdown into active project execution, covering plant upgrades, better feedstock flexibility and preparations for restart, and announced a five-month turnaround beginning on November 1, 2026, with a restart target in the second quarter of 2027. On November 10, Nikkei Asia reported that the group now expects the complex to be back online around mid-2027, later than SCG had initially hoped when it first suspended the site. In Thailand, Rayong Olefins was able to restart in mid-September 2026 after a full review of its operations, but the Vietnamese plant remains offline.

The situation in the Strait of Hormuz remains fragile in November 2026. Transits through the strait rose in October to their highest monthly level since July, but the International Maritime Organization still advises vessels against using the route, and shipping continues to face the threat of Iranian attacks and possible mines. Part of the Gulf naphtha supply has found a way around the bottleneck, with the United Arab Emirates and Kuwait loading cargoes onto ships for transfer off Sohar, in Oman, outside the strait. These workarounds have helped some Asian crackers raise output, but they have not restored the reliability that a plant like Long Son needs to plan its feedstock purchases.

What it means for Vietnam and Asian buyers

While LSP is idle, Vietnamese plastics converters and packaging manufacturers have to rely again on imported polyethylene and polypropylene, as they did before the complex opened, which exposes them to the same freight and price swings that hit the whole region this year. Other domestic producers, such as Hyosung Vina Chemicals and Binh Son, cover only part of local resin demand.

The Long Son decision also illustrates a broader shift in Asian petrochemicals. A plant located about ten days' sailing from the Gulf will soon take most of its feedstock from the other side of the Pacific, because that supply line is now seen as safer. By locking in 15-year ethane supply and shipping contracts, SCG is making a commitment that will outlast any ceasefire or peace agreement in the Middle East. With the Strait of Hormuz carrying around a quarter of global naphtha supply, other Asian producers that depend on Gulf feedstock are facing the same choice between waiting for the route to stabilize and redesigning their supply chains around new origins.

💡 Alternative Solution

Conversion of the cracker to run on up to 70% US ethane, 15-year supply contract for 1 million tonnes of ethane per year with Enterprise Products Partners, 15-year charter of five very large ethane carriers with Mitsui O.S.K. Lines, construction of two 55,000-tonne ethane storage tanks, reduction of Middle East feedstock share below 25%, feedstock purchases from suppliers outside the Strait of Hormuz, maintained flexibility to process naphtha and propane, imports of polyethylene and polypropylene by Vietnamese converters during the shutdown