European PVC Producer Vynova Enters Bankruptcy in Belgium, Beek Plant Seeks Payment Protection

high active production shutdown
📅
Published OnNovember 17, 2026
🌍
LocationBeek, Netherlands
🏭
SupplierVynova Group (LVM Netherlands BV)
📦
SectorPVC Manufacturing
🎯
Impacted ClientEuropean PVC converters (pipes, window profiles, flooring, cables)
⚙️
Critical ComponentPVC resin
💰
Financial Impact$45,000,000

European chlor-vinyls producer Vynova has lost its long fight for survival. On November 10, 2026, Vynova Belgium NV, which runs the chemical complex in Tessenderlo-Ham, filed for bankruptcy after more than ten months of court-supervised restructuring failed to deliver a buyer or a new investor. On the same day, LVM Netherlands BV, the Vynova subsidiary that owns the PVC plant in Beek at the Chemelot industrial park in Dutch Limburg, applied for a suspension of payments under Dutch law, known as surseance van betaling.

The courts acted quickly in both countries. On November 12, the Hasselt division of the Antwerp Enterprise Court declared Vynova Belgium bankrupt and appointed four curators to manage the estate, ending a site that employed around 600 people. That same day, the District Court of Limburg granted LVM Netherlands a provisional suspension of payments and named a court-appointed administrator to oversee the Beek company. A first creditors' meeting for the Dutch entity has been scheduled for December 29, 2026, at 12:00 CET.

The Beek plant has had a troubled two years. The facility, which began operating in 1972 and has a nominal capacity of about 225,000 tonnes per year of suspension PVC, was already targeted for closure in July 2025, when Vynova cited global overcapacity, weak demand and competition from low-cost regions. Production stopped in November 2025, affecting about 100 jobs. The original operating company, Vynova Beek BV, entered suspension of payments at the end of January 2026 and was declared bankrupt on February 10, 2026.

Instead of letting the site disappear, Vynova Belgium set up LVM Netherlands BV in June 2026 to take over the Beek assets and prepare a restart. The plan was to bring the plant back online in October 2026 so that it could be handed over as a working business to a future investor. That plan did not survive the autumn. In late October, Vynova announced a phased shutdown of its Tessenderlo-Ham complex, with a full production pause targeted for November 5, and said it would complete the technical preparations at Beek but keep the restart on hold. The company blamed exceptionally high energy prices that had drained its financial reserves.

The Belgian collapse followed a long legal process. Vynova Belgium entered judicial reorganization on December 26, 2025, with debts estimated at around 275 million euros. The court extended the protection from creditors several times, including a third extension granted on September 8, 2026, which kept the company shielded until December 26, 2026. Under that schedule, Vynova had to file a restructuring plan by November 13, and creditors were set to vote on it on December 4. Negotiations with several interested parties, including the Dutch salt and chlor-alkali group Nobian, ended without a deal, and the company chose to file for bankruptcy weeks before the vote. Vynova pointed to three main causes: high and volatile energy prices, persistently weak demand, and rising imports from regions with lower production costs.

The bankruptcy matters well beyond Tessenderlo because the three remaining Vynova sites form a single integrated PVC chain. The Belgian complex produces ethylene dichloride (EDC) and vinyl chloride monomer (VCM), the two key building blocks of PVC. VCM is sent by a dedicated pipeline from Tessenderlo to Beek and by rail to Mazingarbe in northern France, where it is turned into PVC resin. With the Belgian plant idle and now in the hands of curators, the Beek facility has no feedstock of its own, which makes any restart at Chemelot dependent on what happens to the upstream assets in Belgium.

In France, Vynova Mazingarbe SAS is assessing the consequences of the Belgian bankruptcy and says it will take the necessary steps under French law in consultation with employee representatives. The Mazingarbe plant is authorized to produce up to 350,000 tonnes per year of specialty PVC grades and produced about 212,000 tonnes in 2024. Because it relies on VCM delivered from Tessenderlo, its operations are also exposed, although no French insolvency filing or permanent closure has been announced so far.

The group had already shrunk significantly before this latest blow. Its German site in Wilhelmshaven went through insolvency proceedings and was acquired by Westlake in June 2026, keeping about 380,000 tonnes per year of PVC capacity in Europe under new ownership. In the United Kingdom, INEOS Inovyn completed the purchase of Vynova's EDC assets in Runcorn and its remaining stake in a joint chlor-alkali venture on October 30, 2026.

For the European market, the loss of Tessenderlo removes a significant source of VCM and EDC at a time when regional PVC producers are already under pressure from high energy costs and cheaper imports from the United States and Asia. Converters that make pipes, window profiles, flooring, cables and medical products are likely to rely more on other European suppliers and on imported resin, which can mean longer lead times and less flexibility for buyers. The Belgian chemical federation has described the Vynova case as a symptom of a wider crisis affecting energy-intensive industry across Europe, while the Flemish government has blamed high energy prices and pledged to support efforts to keep industrial activity on the Tessenderlo site.

As of mid-November 2026, the situation remains unresolved in all three countries. In Belgium, the curators are now in charge of the estate and will decide whether parts of the complex can be sold or restarted by a new owner. In the Netherlands, the administrator of LVM Netherlands is assessing whether a buyer can still be found for the Beek plant before the December 29 creditors' meeting, and a suspension of payments can still turn into a full bankruptcy if no viable solution emerges. In France, the future of Mazingarbe depends largely on access to VCM. Market participants are closely watching asset sales, the timing of any plant closures and how quickly other suppliers can fill the gap left by one of Europe's integrated PVC chains.

💡 Alternative Solution

Sourcing PVC resin from other European producers such as INEOS Inovyn, Westlake and Kem One, increasing imports of PVC resin and VCM from the United States and Asia, qualifying alternative resin grades with downstream converters, building safety stocks, and monitoring the sale of the Tessenderlo, Beek and Mazingarbe assets to a new investor

Published on November 17, 2026